The Prompt Payment Act requires a federal agency to pay a proper invoice within 30 days of receiving it, to return a defective invoice within 7 days, and to add interest automatically when it pays late. The rules are in 5 CFR Part 1315 and FAR Subpart 32.9; the penalty rate is 4.75% for July 1 through December 31, 2026 (Treasury Fiscal Service).
What the Act does not do is fund payroll for those 30 days, or the 45 to 75 it often takes in practice. That gap is why government contract financing exists.
Amounts, rates and terms shown are illustrative examples, not an offer or a quote. Select Loan Advisors is not a lender; funding partners set all terms. See how we're compensated.
| Event | Rule | Source |
|---|---|---|
| Invoice "received" | The later of actual receipt or the 7th day after delivery or completion of services | 5 CFR 1315.4(b) |
| Improper invoice | Returned within 7 days with every defect that prevents payment; the clock restarts on the corrected invoice. If the agency misses the 7 days, the due date is adjusted against it | 5 CFR 1315.4(c); FAR 32.905(b)(3) |
| Acceptance | Deemed to occur on the 7th day after delivery or performance if the agency has not acted | FAR 32.904(b) |
| Due date | 30 days after receipt of a proper invoice unless the contract says otherwise; weekend or holiday due dates roll to the next business day | 5 CFR 1315.4(g), (h) |
| Early payment | Small businesses may be paid "as quickly as possible" once documents are matched | 5 CFR 1315.5(b) |
Late payment interest is automatic (FAR 32.907), but "30 days" runs from a proper invoice and interest accrues only after acceptance (5 CFR 1315.10(b)(1)).
5 CFR 1315.9(b) lists the required contents: vendor name and invoice date; contract number; invoice number or other agreed identifier; description, price and quantity, including the contract line item number; shipping and payment terms; Taxpayer Identification Number; EFT banking information; a contact name, title and phone number; and any other documentation the contract requires, such as a receiving report or timesheets.
Most late payments trace to a missing CLIN, a mismatch with the receiving report, or the wrong billing office, not to the agency.
Treasury sets the rate every six months. Interest runs from the day after the due date through the payment date on a 360-day year; unpaid interest is added to principal every 30 days for up to one year, and penalties under $1 are not paid (5 CFR 1315.10).
Worked example. A proper $120,000 invoice is received June 1, due July 1, and paid July 21, 20 days late, while the rate is 4.75%.
If the agency pays the $120,000 but not the interest within 10 days, and you request it in writing by the 40th day after payment, an additional penalty equal to 100% of the interest applies, with a $25 floor and a $5,000 cap (5 CFR 1315.11): another $316.67 here.
Carrying the same $120,000 privately for 20 days costs about $120,000 × 12% × 20 ÷ 365 = $789 on a line at Prime + 5.25% (12.00% at the current 6.75% prime), or $1,200 in factoring fees at 1.5% per 30 days. The Act's interest is real money, but it does not cover your financing cost and never arrives before the principal.
No interest is owed on disputed amounts (FAR 32.907), on contract financing payments (FAR 32.007), or after a Contract Disputes Act claim is filed or one year has passed, whichever comes first.
The Act sets a 30-day floor on your cash cycle; acceptance, resubmissions and month-end billing push it to 45 to 75 days in practice.
Illustrative. A services contractor bills $120,000 a month on a $1,440,000 contract; weekly payroll is $20,000. The first invoice goes in on day 30 and, after acceptance and one correction, is paid on day 75. Ten payrolls ($200,000) go out before the first $120,000 comes in; from then on about $150,000 of payroll is always ahead of collections.
| Option | Timing | Illustrative cost | Notes |
|---|---|---|---|
| Wait and collect Prompt Payment interest | 30 days minimum; interest only if late | $0 out of pocket; 4.75% on late days only | Does not fund payroll |
| Government contract factoring, 90% advance, 1.5% per 30 days | $108,000 within 48 hours of each accepted invoice | 45-day fee 2.25% × $120,000 = $2,700 per invoice | Requires an assignment of claims; the agency pays the factor |
| Contract-backed line at Prime + 5.25% (12%) | Draws as costs are incurred, from day one | $150,000 average × 12% = $18,000 a year | Covers pre-invoice payrolls; 2 to 6 weeks to set up |
| Progress payments under FAR 32.5, 85% of costs | Monthly requests | $0 | Only if the clause is in the contract |
Bill on the first eligible day, confirm receipt and acceptance with the billing office, and ask to be paid early under 1315.5(b). If the principal arrives without interest, request it in writing within 40 days. None of that replaces a facility sized to the gap.
The Act runs between the agency and the prime. Outside construction, a subcontractor's only protection is the payment clause in the subcontract: negotiate a fixed number of days after the prime is paid, not "pay if paid," and ask the prime to acknowledge your lender as payee, since a sub cannot assign claims against the government. Firms with 8a certification are paid on the same 30-day clock; the certification affects award, not payment timing.
Thirty days after the designated billing office receives a proper invoice, unless the contract sets a different period. Receipt is the later of actual receipt or the 7th day after delivery or performance. Construction progress payments are due in 14 days.
The Treasury rate for July 1 through December 31, 2026 is 4.75%, reset every January 1 and July 1. Interest runs from the day after the due date through the payment date on a 360-day year, and unpaid interest compounds every 30 days for up to one year.
Multiply the unpaid amount by the Treasury rate, divide by 360, and multiply by the days late. A $120,000 invoice paid 20 days late at 4.75% earns $120,000 × 0.0475 ÷ 360 × 20 = $316.67. If the agency pays the principal but not the interest within 10 days, request the additional penalty in writing within 40 days; it equals the interest, with a $25 minimum and a $5,000 maximum.
No. Contract financing payments, including progress payments under FAR 32.5 and performance-based payments under FAR 32.10, are excluded from interest penalties by FAR 32.007. They are due on the 30th day after a proper request unless the agency sets a period of 7 to 30 days.
The agency must return an improper invoice within 7 days of receipt and identify every defect that prevents payment. The 30-day clock restarts when the corrected invoice is received. If the agency takes longer than 7 days, the due date is adjusted so the extra days count against the agency for interest purposes.
If your invoices are proper and the agency is simply slow, the Act will get you paid with interest. If payroll cannot wait 30 to 75 days, we size a factoring or contract-backed line to the gap and tell you when the margin will not carry it. Read how business loan brokers work and how do business loan brokers get paid, then
Check My Options →