Construction contract financing on a government job has to solve four problems at once: mobilization costs before the first pay application, weekly Davis-Bacon payroll against monthly progress payments, retainage of up to 10% held until the end, and a surety with a claim on the contract funds. The structures on our government contract financing hub all apply, but construction receivables draw lower advances and closer scrutiny, and the bond changes what a lender can take.
We are advisors, not a lender or surety; see how we're compensated. Amounts, rates and terms shown are illustrative examples, not an offer or a quote. Select Loan Advisors is not a lender; funding partners set all terms.
Three clauses set the cash cycle.
Each payment request also certifies that subs and suppliers have been paid from previous payments and will be paid from this one.
On a $2 million contract with 10% retainage, $200,000 of earned revenue sits with the government until completion or until the contracting officer reduces retainage for satisfactory progress. At a 12% gross margin, that is most of your profit for the entire job.
Financing options are limited. Factors advance only on net billable amounts, never on retained sums. A contract-backed line may count retainage in the borrowing base at a low advance rate near completion if no claims are pending. The practical fix is to request a retainage reduction once progress is satisfactory, which the clause permits, and to bid with the retainage carry priced in.
Site setup, bonds, insurance, equipment rental and the first payrolls all happen before the first pay application. Some solicitations include a mobilization line item that can be billed early; many do not. Where there is none, mobilization funding covers the first 30–60 days and is repaid from the first progress payments or factoring advances. Size it to the real pre-billing gap.
A bond and a loan are not the same thing.
| Surety bond | Contract financing | |
|---|---|---|
| What it is | A guarantee to the government that you will perform and pay subs and suppliers | Cash advanced to you against the contract |
| Who it protects | The government (performance bond); your subs and suppliers (payment bond) | You |
| Required by | FAR 28.102-1: Miller Act bonds on construction contracts over $150,000; alternative payment protections from $35,000 to $150,000 | Nobody; your choice |
| What you pay | A premium, a percentage of the contract price | Interest or fees on money used |
| Puts cash in your account | No | Yes |
| Claim on contract funds | The surety, if you default | The lender, by assignment under FAR 32.8 |
The two interact. Under FAR 32.805, the lender forwards its notice of assignment to every party listed in FAR 32.802(e): the contracting officer, the surety on any bond, and the disbursing officer. Sureties want to know about, and sometimes consent to, contract financing, because an assignment redirects funds they rely on if they have to finish the job. Tell your bonding agent before you sign; an undisclosed assignment can tighten or pull your capacity.
It runs in reverse too: sureties size capacity on working capital and net worth, so a line that improves liquidity can raise the program, and expensive daily-payment debt can lower it.
On a construction job, cash speed is mostly paperwork. Submit the pay application on the first billable day of each month. Match the schedule of values to how the inspector measures progress, because disputed line items delay the whole payment. Include the subcontractor payment certification and certified payrolls; a request missing documents is not a proper invoice, and the 14-day clock does not start. Then track the 14 days: under 5 CFR 1315, interest accrues automatically on late payments, currently 4.75% through December 31, 2026 per the Treasury Fiscal Service. Every day cut from the billing cycle is a day less of financing cost.
FAR 52.222-6 requires that laborers and mechanics on the site "be paid unconditionally and not less often than once a week," and FAR 52.222-8 adds weekly certified payrolls with a signed Statement of Compliance. You cannot slow payroll to match the government's monthly cycle.
An illustrative site contractor on a $1.8 million federal renovation over 12 months:
Month one: four payrolls, $88,000, plus roughly $40,000 of mobilization, before any invoice exists. The first $135,000 arrives around day 48. By then the contractor has paid seven payrolls, $154,000, plus mobilization: about $194,000 out against $135,000 in. The steady-state gap is about seven weeks of payroll, roughly $150,000, and retainage grows $15,000 a month on top, reaching $180,000 by completion.
A contract-backed line of $200,000 at an illustrative 12% (Prime + 5.25% at 6.75% prime) carrying an average $150,000 balance costs about $1,500 a month, $18,000 over the job, plus fees. Factoring the net pay application at a 75% advance and 2.5% per 30 days yields about $101,000 per request within two days, at a fee of roughly $2,025 for 18 days (0.6 × 2.5% × $135,000); about $24,000 over 12 months. Both are affordable on an 18% margin ($324,000 of gross profit). Neither is affordable on a 6% margin.
A prime finances against the agency's obligation with a federal assignment noticed to the surety. A sub finances against the prime's obligation with a commercial assignment and, on bonded jobs, the Miller Act payment bond as backstop. Factors advance less on sub invoices and want the prime's acknowledgment.
See how business loan brokers work for what happens after the soft credit pull.
Rarely, and never through factoring, which advances only on net billable amounts. Some contract-backed lines include retainage in the borrowing base at a low advance rate near completion when no claims are pending. The better tool is FAR 52.232-5 itself, which lets the contracting officer reduce retainage once progress is satisfactory. Ask for that reduction in writing.
No. A performance bond guarantees the government the job will be completed; a payment bond guarantees subs and suppliers they will be paid. Neither puts cash in your account. You pay a premium and indemnify the surety for any loss. Financing is the separate tool that provides cash, and sureties care about it because an assignment of contract proceeds affects funds they rely on if they have to step in.
Consent depends on your bond terms, but notice is mandatory. FAR 32.805 requires the assignee to send the notice of assignment to the surety on any bond as well as to the contracting officer and disbursing officer. Discuss any financing with your bonding agent before signing; undisclosed assignments are a common reason sureties restrict capacity.
Under FAR 52.232-27, progress payments are due 14 days after the designated billing office receives a proper payment request, and final payment 30 days after a proper final invoice. Improper requests are returned and the clock restarts on resubmission. Late payments accrue Prompt Payment interest, currently 4.75% through December 31, 2026.
Because it fixes your payroll cycle at weekly. FAR 52.222-6 requires covered workers on the site to be paid not less often than once a week, and FAR 52.222-8 requires weekly certified payrolls. Against monthly progress payments arriving two to three weeks after the month closes, that creates a gap of six to eight weeks of payroll to be carried by cash or financing.
Send us the award, schedule of values, bond details and weekly payroll. We will map the gap month by month, tell you which structure your surety will accept, and place the file with partners that handle bonded government construction.